How to insert the Risk Report at the Top of Programs Checklists?

How to insert the Risk Report at the Top of Programs Checklists?

Identified risks are can be assigned to the relevant program / checklist by using the Addressed/Reference field in the Risk dialog. This allows the user to view the risks associated with each financial statement while in the program or checklist.

1. Ensure the appropriate program / checklist has been addressed in the Risk dialog. 



2. Open the appropriate program / checklist. 

3. From the audit menus, select Areas | Risk Report > Insert Risk Report. The risk report will appear above the program / checklist. 



  • The risk report will not print by default. From the audit menus, select Options | Print Risk. The risk item will now appear in black. 
  • Business and Fraud risks display in all programs / checklists if the Risk Report is active.